Construction Updates

External rendering of Fulton from the south.

Project Details

Fulton is creating additional space to accommodate the full-day kindergarten program. Additions will be made on two locations of the existing building: on the west side of the building, and off of the gymnasium.

Additions include:

  • Two kindergarten classrooms with restrooms
  • New early learning playground equipment with outdoor storage
  • A new music room

Fulton Construction Drawing
Please click the image above for a larger version.

Timeline

Construction began in May 2018 and will be completed in May 2019.

Updates

Please check back regularly for continued updates on the construction at Fulton School. 

January 14, 2019

Roofing work on both additions has been completed. Power to three existing parking lot light poles was reestablished. Electrical, plumbing, and mechanical rough-in work continues in both additions.

January 4, 2019

Cement blocks have been installed in window openings of the exiting kindergarten rooms, and the new walls have been painted. A new doorway that joins the new and old music room storage closets together has been installed. The interior and vestibule doors by the new music rooms have been installed.

December 21, 2018

Angled corner bricks have been installed on the music room addition, and roofing on the kindergarten addition has begun. Windows in the new kindergarten hallway have been installed. Interior framing, electrical, pluming, and mechanical rough-in work continues in both additions. 



November 30, 2018

The installation of the exterior masonry block insulation on the kindergarten addition was completed. Carpenters completed the installation of the roof soffit on the music room addition, and the installation of the music room roof was finished. The installation of face brick on the kindergarten addition and the music room is nearing completion.

Interior framing in the music room continues and interior framing work in the kindergarten addition has begun. Electricians, plumbers and the mechanical contractors continue rough-in work in both additions.

November 9, 2018

Carpenters began installing the roof soffit on the Music room addition. The steel roof joists and roof decking was completed on the Kindergarten addition.

October 18, 2018

The masonry block work continues on the Kindergarten addition, and the installation of the exterior masonry block insulation has begun. The Music room's steel roof joist installation has begun and the installation of the masonry face brick has been started.

October 15, 2018

Masonry block work continues on the kindergarten addition. The music room block work is 90% complete. The door frames have been installed and the exterior foam insulation is complete. In the coming weeks, roof joists and decking will be installed on both additions, and the block masonry work is scheduled to be completed.


September 10, 2018

Masonry work and electrical rough-in continues on the music room.
The kindergarten room addition was excavated and the concrete footings and foundation walls have been poured. The underground plumbing is set to begin this week in the kindergarten addition and steel roof joists and roof decking is scheduled to start.

August 20, 2018

Underground electrical work was completed for the music room addition and the concrete floor is finished. Masonry work on the walls is in progress. Water main relocation work has been completed and natural gas main relocation is scheduled will follow.

August 6, 2018

 

The music room excavation, footings, and foundation walls have been completed. Underground electrical work in the music room will soon be complete and will be followed by the music room concrete floor.

Site work and excavation related to the enlargement of the water detention area to the south of the main playground continues. 

July 16, 2018

The installation of storm sewer lines and catch basins, and sanitary lines and catch basins has begun.

July 2, 2018

Construction fencing has been installed around the construction areas and early learning playground fencing and equipment removal has been completed.

The demolition and excavation of sidewalks and playground asphalt along with the demolition of the canopy over Door 13 has been completed.

 