Construction Updates

External rendering of Fulton from the south.

Project Details

Fulton is creating additional space to accommodate the full-day kindergarten program. Additions will be made on two locations of the existing building: on the west side of the building, and off of the gymnasium.

Additions include:

  • Two kindergarten classrooms with restrooms
  • New early learning playground equipment with outdoor storage
  • A new music room

Fulton Construction Drawing
Please click the image above for a larger version.

Timeline

Construction began in May 2018 and will be completed in May 2019.

Updates

Please check back regularly for continued updates on the construction at Fulton School. 

October 15, 2018

Masonry block work continues on the kindergarten addition. The music room block work is 90% complete. The door frames have been installed and the exterior foam insulation is complete. In the coming weeks, roof joists and decking will be installed on both additions, and the block masonry work is scheduled to be completed.


September 10, 2018

Masonry work and electrical rough-in continues on the music room.
The kindergarten room addition was excavated and the concrete footings and foundation walls have been poured. The underground plumbing is set to begin this week in the kindergarten addition and steel roof joists and roof decking is scheduled to start.

August 20, 2018

Underground electrical work was completed for the music room addition and the concrete floor is finished. Masonry work on the walls is in progress. Water main relocation work has been completed and natural gas main relocation is scheduled will follow.

August 6, 2018

The music room excavation, footings, and foundation walls have been completed. Underground electrical work in the music room will soon be complete and will be followed by the music room concrete floor.

Site work and excavation related to the enlargement of the water detention area to the south of the main playground continues. 

July 16, 2018

The installation of storm sewer lines and catch basins, and sanitary lines and catch basins has begun.

July 2, 2018

Construction fencing has been installed around the construction areas and early learning playground fencing and equipment removal has been completed.

The demolition and excavation of sidewalks and playground asphalt along with the demolition of the canopy over Door 13 has been completed.